Kaufman & Broad's Construction Schedule To Build The Simpson
House
- April 1997 - Kaufman & Broad Home Building, FOX Broadcasting, FOX
Interactive and Pepsi-Cola Company brainstorm on concept for joint
promotion to celebrate THE SIMPSONS' ninth season premiere and Kaufamn and
Broad's 40th anniversary.
- April 11 - Kaufman & Broad Architecture Group commissioned to design
floorplans.
- April 13 - Kaufman & Broad design team watches 96 episodes of The
Simpsons.
- April 20 - Site determined - Henderson, NV - just outside of Las Vegas
Kaufman & Broad renames community "Springfield."
- April 24 - Schematic design complete - Conceptual floor plans issued.
- May 13 - Construction documents submitted to the City of Henderson for
Plan Check.
- Late May - Building permit issued. (City actually says "Yes!")
Construction begins.
- June 2 - House staked.
- June 7 - Foundation trenched and concrete poured.
- June 10 - Underground utilities and post tension cables placed.
Architectural interiors and detailing reviews by Kaufman and Broad project
team.
- June 14 - Concrete floor slab poured.
- June 17 - First floor framing completed.
- June 18 - Second floor framing completed.
- June 20 - Windows installed and heating ducts roughed in. Project team
completes frame walk and review of furnishing and fixtures.
- June 28 - House passes City framing inspection.
- July 5 - Exterior lathing and building inspection completed. Drywall
begins.
- July 10 - Exterior stucco complete and garage door installed.
- July 12 - Drywall complete. Interior doors trimmed and cabinets and
counter tops installed.
- July 14 - Interior and exterior painted.
- July 15 - Trim out electrical and plumbing fixtures. Layout roofing.
- July 16 - Start installation of landscaping, fencing and concrete
flatwork.
- July 21 - Begin installation of set designer fixtures and furnishings.
- July 28 - Set gas and electric meters. Start up air-conditioning.
Finish landscaping.
- July 29 - Installation of fixtures and furnishing completed.
- August 1 - Simpson House completed 49 days after the concrete
foundation was poured.